Takeoff Studio Pro

Assemblies and the NRM2 billPRO

An assembly turns one measurement into every item it needs - a stud partition into boards, studs, track, screws and labour - with formulas, waste and rates. Then make an Excel bill of quantities in NRM2 work-section order, with live formulas, so it recalculates as you type rates.

A stud partition, block wall and slab measured in Takeoff Studio Pro with their assemblies, and the NRM2 bill dialog choosing work sections
How it works

Step by step

1

Measure and pick an assembly

Select a markup, choose an assembly under Assemblies in the Selection tab and click Add. Four come with the app: Stud partition, Concrete slab, Block wall and Skirting.

2

Set the variables

Change the height, spacing or thickness right there, or click Edit for the full recipe: each item has a formula, a unit, waste and a rate.

3

Check the schedule

The items appear under their markup in the Schedule with quantities and costs, and go into the exports and Send to BOQ.

4

Make the NRM2 bill

In the Schedule tab choose NRM2 bill. Takeoff Studio picks a work section for each item from its name, tag and trade package - change any of them - and writes the Excel bill.

5

Price it in Excel

Amounts are Qty x Rate formulas, as are the section totals, the Collection and the Summary, so the bill recalculates as you type rates.

A legend of colours, names and quantities placed on a measured drawing in Takeoff Studio Pro

Help: Rooms, assemblies and NRM2 has every option in detail.

The four preset assemblies

What comes with the app

Metric values; change the variables to suit. Download them as a tool library from the downloads page.

Stud partition on a length along the wall line

Variables: Height = 2.4, Spacing = 0.6, SheetWidth = 1.2, SheetHeight = 2.4, Sides = 2

ItemUnitFormulaWasteRound up
12.5mm plasterboard sheetsnrLength * Height * Sides / (SheetWidth * SheetHeight)10%Yes
Metal studs at centresnrceil(Length / Spacing) + 10%
Head and floor trackmLength * 25%
Drywall screws (approx. 30 per m2 per side)nrLength * Height * Sides * 3010%Yes
Joint tapemLength * Height * Sides * 1.610%
LabourhrLength * Height * 0.450%

Concrete slab on an area

Variables: Thickness = 0.15, MeshLap = 0.1

ItemUnitFormulaWasteRound up
In-situ concrete C32/40 in slabm3Area * Thickness5%
A393 mesh reinforcementm2Area * (1 + MeshLap)0%
1200 gauge DPMm2Area10%
Edge formworkmPerimeter0%

Block wall on a length along the wall line

Variables: Height = 2.4, BlocksPerM2 = 10

ItemUnitFormulaWasteRound up
100mm dense concrete blockworkm2Length * Height0%
BlocksnrLength * Height * BlocksPerM25%Yes
Mortarm3Length * Height * 0.0110%
Wall ties / reinforcement every 3rd coursemLength * ceil(Height / 0.675)5%

Skirting on a length along the wall line

Variables: Doors = 0, DoorWidth = 0.9, BoardLength = 4.2

ItemUnitFormulaWasteRound up
MDF skirting boardmmax(0, Length - Doors * DoorWidth)10%
Skirting lengthsnrmax(0, Length - Doors * DoorWidth) / BoardLength10%Yes
Decoration to skirtingmmax(0, Length - Doors * DoorWidth)0%
Who it's for

Made for

Part of Takeoff Studio Pro. Measuring in Takeoff Studio is free. Pro is £24.99 a month or £199.99 a year, the first month is free, and you can cancel any time from your Microsoft account.

Guides

Related how-to guides

Frequently asked questions

What can a formula use?

Qty, Length, Area, Perimeter, Count, Height, Depth, Volume and your own variables, with + - * / ^, brackets and ceil, floor, round, min, max, abs, sqrt and if. For example ceil(Length / Spacing) + 1 studs.

How is waste added?

Waste % is added after the formula, then Round up makes it a whole number if you tick it. Formulas work on one unit of the markup; Times multiplies the results.

Which NRM2 work sections does it use?

Sections 2 to 41 in NRM2 order - 11 In-situ concrete works, 14 Masonry, 20 Proprietary linings and partitions, 28 Floor, wall, ceiling and roof finishings, 29 Decoration and so on - with units m, m2, m3, nr and t. Items it can't place go in an Other items section for you to assign.

Can I reuse my own assemblies?

Yes. Save an assembly to the project library, or save the markup as a tool to keep its assemblies in your tool library and share it with your team. The four preset assemblies are on the downloads page as a tool library.

Do I need Takeoff Studio Pro?

Yes, assemblies and the NRM2 bill are part of Takeoff Studio Pro (£24.99 a month or £199.99 a year, first month free). There's also a free NRM2 bill template for Excel on the downloads page.