How the dates are checked

  • Hand-worked cases: a small programme for every link type (FS, SS, FF, SF), lags and leads, each constraint type, calendar edges such as shutdowns, bank holidays and part days, and both ways of handling out-of-sequence progress, with the dates and float worked out by hand.
  • Against P6 and MS Project: programmes saved by Primavera P6 and Microsoft Project carry the dates those programs calculated. Programme Studio reschedules each one from its own logic and calendars and compares every activity's dates and float, to the working day.
  • Round trips: XER to Programme Studio to XER, and the same for P6 XML, MS Project XML, MPX, Excel, CSV and IFC, keep the dates and every field read. In an XER, the tables Programme Studio doesn't edit are written back byte for byte.
  • In the browser: Playwright drives the app itself - typing, linking, dragging bars, filters, undo, printing, the free limit, the start screen and a 5,000-activity scrolling budget - and fails on any page error.

Results against P6 and MS Project

Reference fileSaved byActivitiesCheckedResult
Percent complete (P6 XML)Primavera P6 8.412Early start and finish of every activity, with in-progress work on duration, physical and units percent complete12 of 12 match
Task links (MPX)MS Project 9816Early and late dates with every link type and lags in days and weeks16 of 16 match
Task durations (MPX)MS Project 9890Early and late dates for durations in minutes to months90 of 90 match
Durations (MS Project XML)MS Project10Finish dates, including elapsed durations that run round the clock10 of 10 match
Riverside Health Centre (XER and MS Project XML)Metre2 Gantt Viewer tests34Early start and finish, late start and finish and total float against the dates saved in the file, with progress at a data dateAll match: 34/34 early dates, 26/26 late starts, 27/27 late finishes, 27/27 total float

Where a P6 file's own dates are not P6's answer (for example a programme saved without being rescheduled), it is not used as a reference. Late dates of work already complete are a display convention in P6 and are not compared.

The automated checks

AreaChecks
Scheduling engine: link types, lags and leads, constraints, calendars, part days, progress modes, float45
File import and export: XER, P6 XML, MS Project XML, MPX, IFC, GanttProject, round trips56
Excel and CSV import and export21
Exchange between formats16
Logic checks26
Progress, baselines and revisions26
Activity codes and user fields32
Delay analysis: time impact, windows, what-if, the 14-point check, NEC438
Resources, levelling, cost and earned value34
Last Planner and takt23
Printing23
Total340

Plus 157 checks in a real browser: 102 for the workspace, 47 for the free version and 8 for the .mpp conversion. All of them run before every release.

What has not been checked yet

The reference programmes are test files, from Metre2's own tests and the open-source MPXJ project's test data, not large live construction programmes. Programme Studio follows P6's documented scheduling options, but P6 has settings and edge cases (resource-dependent activities, some level-of-effort behaviour, multiple float paths) that the reference set does not yet cover.

If you have an XER or MS Project file you are happy to share, scheduled in P6 or MS Project, it can go straight into the comparison: email support@metre2.co.uk. It is used for testing only and never published.