Time-chainage programmes for roads and pipelines

Roads, railways, pipelines and cable routes are built along a line, and what matters is where each crew is and when: whether the drainage gang is far enough behind the earthworks, when the traffic management can move. A time-chainage (or time-distance) diagram puts chainage along one axis and time down the other, so each operation is a line moving along the job. Metre2 Programme Studio Pro draws it from the programme's activities and their chainages, so it stays in step with the logic.

4 stepsProVideo 22 seconds

What you need

Step by step

1

Start from your programme or the template

Open your programme, or choose Highways and drainage on the start screen: earthworks, drainage runs, kerbs, sub-base and surfacing over two sections between chainage 0 and 500, with traffic management phases.

Start from your programme or the template - Metre2 Programme Studio
2

Show the time-chainage view

Choose View > Time-chainage. Chainage runs across the top (0+000 to 0+500) and time down the side. Each operation is a line from where it starts to where it ends; areas occupied for a time, such as a traffic management phase, can be drawn as blocks. Ctrl and the mouse wheel zoom in time.

Show the time-chainage view - Metre2 Programme Studio
3

Pick an operation

Hover over a line for its dates, chainage and float, and click it to select it. Its properties, logic and float open on the right, and it is the same activity as in the Gantt chart.

Pick an operation - Metre2 Programme Studio
4

Set where it goes

In the properties panel, Chainage from and Chainage to are in metres, and Shape chooses a line (work moving along) or a block. Here the section 2 drainage is extended to 560 m and the diagram follows straight away.

Set where it goes - Metre2 Programme Studio

Tips

Frequently asked questions

What is a time-chainage diagram?

A programme for linear projects drawn with distance along the route (chainage) on one axis and time on the other. Each activity is a line or block showing where along the route the work happens and when, so the movement of crews along the job can be planned and checked.

What is chainage?

The distance along a road, railway, pipeline or other route from a fixed start point, usually written as kilometres plus metres, such as 0+250 for 250 metres.

Is time-chainage the same as time-location or time-distance?

Yes, they are names for the same kind of diagram. Line of balance is its relative for repeated locations such as plots or floors.