Bays and lifts

A bay is the gap between two pairs of standards along the face; a lift is the vertical gap between ledgers. A 12 m elevation with 2.1 m bays needs 12 ÷ 2.1 = 5.7, so 6 bays. An 8 m height with 2 m lifts needs 4 lifts. A working lift is one that's boarded out with guardrails and toe boards.

The counting rules

ComponentRule (two rows of standards)
Standards and base plates(bays + 1) × 2
Ledgersbays × lifts × 2
Transoms(bays + 1) × lifts
Boards per working liftboards wide × boards per bay length × bays
Guardrails per working liftmain and intermediate rail along each bay, plus 2 at each end
Toe boards per working liftbays + 2
Right-angle couplers2 per ledger, transom and guardrail
Brace tubes and swivel couplers1 brace per lift in the end bay, 2 swivels each
Tiesabout one per 4 m along every second lift (check the design)

Worked example

A 12 m long, 8 m high elevation, 2.1 m bays, 2 m lifts, 5 boards wide, with 2 working lifts.

ItemQuantity
Bays × lifts6 × 4
Standards14
Base plates14
Ledgers48
Transoms28
Boards (2.4 m)60 (30 per lift)
Guardrails32
Toe boards16
Brace tubes4
Right-angle couplers216
Swivel couplers8
Ties6

Add sole boards under the base plates, ladder access or a stair tower, and any loading bay. The Scaffolding Quantity Calculator works these counts out from the same inputs and draws the elevation so you can check them.

Safety and compliance

These are estimating quantities, not a scaffold design. In the UK, scaffolds must be erected, altered and dismantled by competent, trained scaffolders (CISRS cardholders), follow the NASC TG20 guidance or a bespoke design, and be inspected under the Work at Height Regulations 2005 before first use, after alteration and at least every 7 days. Tie patterns, loading class and bracing come from the TG20 compliance sheet or the designer, not from a rule of thumb.