Mortar per square metre

WorkWet mortar per m²
Brick, single skin (half brick), 10 mm joints0.032 m³
Brick cavity wall, both skins0.055 m³
100 mm blockwork0.014 m³
140 mm blockwork0.017 m³
Render, per 10 mm coat0.010 m³
Repointing0.006 m³

These are the figures the Mortar Mix Calculator uses. Bricks use far more mortar per m² than blocks because there are about 60 bricks to a square metre against 10 blocks.

Choosing the mix

DesignationCement:lime:sandTypical use
M12 (i)1:0.25:3Below DPC, engineering brick, retaining walls
M6 (ii)1:0.5:4.5Exposed work, parapets, chimneys
M4 (iii)1:1:6General brick and blockwork above DPC
M2 (iv)1:2:9Internal, low-exposure work

Use the mix the drawings or the brick manufacturer specify. A mortar much stronger than the bricks makes cracks go through the bricks rather than the joints.

From wet volume to bags and tonnes

  1. Wet volume = area × mortar per m².
  2. Dry volume = wet volume × 1.3 (the dry materials bulk down when mixed), plus waste.
  3. Split the dry volume by the mix parts. A 1:1:6 mix has 8 parts: cement 1/8, lime 1/8, sand 6/8.
  4. Cement: one 25 kg bag is about 0.0175 m³. Hydrated lime: one bag is about 0.05 m³. Sand: about 1.6 tonnes per m³.

Worked example

25 m² of half-brick facing wall and 15 m² of 100 mm blockwork, in 1:1:6 with 10% waste.

StepWorkingResult
Wet volume25 × 0.032 + 15 × 0.0141.01 m³
Dry volume, +10% waste1.01 × 1.3 × 1.101.444 m³
One part (of 8)1.444 ÷ 80.181 m³
Cement0.181 ÷ 0.017511 bags (25 kg)
Lime0.181 ÷ 0.054 bags
Sand6 parts = 1.08 m³ × 1.61.73 tonnes

Order 11 bags of cement, 4 of lime and a 2 tonne bulk bag of building sand.