Building pad formation level from the FFL

The architect gives a finished floor level (FFL); the groundworker digs to formation, the level under the slab and stone. The difference is the floor build-up, and the dig runs out past the slab by a working space before the batters start. This guide sets the FFL, the build-up and the working space of a warehouse pad in Metre2 Earthworks Pro and reads the formation and the volumes.

6 stepsProVideo 20 seconds

What you need

Step by step

1

Select the building pad

Draw a Building pad round the slab (Design tab), or select one. The Unit 4 sample is a 120 x 60 m distribution shed on a 1 in 40 slope.

Select the building pad - Metre2 Earthworks
2

Type the FFL

Set the Finished floor (FFL): 33.900 here.

Type the FFL - Metre2 Earthworks
3

Set the floor build-up

The floor build-up is everything between the FFL and formation: slab, insulation, membrane, sub-base. 650 mm here, so formation is 33.250.

Set the floor build-up - Metre2 Earthworks
4

Add the working space

Working space is how far the dig runs beyond the slab edge to give room for shuttering and drainage: 1 m here. The formation is widened by it, and the batters start from there.

Add the working space - Metre2 Earthworks
5

Check why

The Why this formation? note spells it out: finished level less build-up, widened for working space. The pad now needs 2,538 m³ of cut and 3,899 m³ of fill to formation.

Check why - Metre2 Earthworks
6

Look at a section

Section through shows the ground, the FFL, the formation and the batters across the pad.

Look at a section - Metre2 Earthworks

Tips

Frequently asked questions

What is formation level?

The level the earthworks are finished to, ready for the construction on top: the underside of the sub-base under a slab, road or car park. It's the finished level less the build-up.

What is working space?

Extra width dug beyond the edge of a slab or foundation so people can work there. It's measured in NRM2 as part of the excavation.

Is it in the free version?

Building pads with build-up and working space are in Earthworks Pro (£19.99 a month or £179 a year, with a 7-day free trial). The free version has platforms and slope areas.

Is my survey uploaded?

No. Earthworks runs in your browser: survey files, LIDAR tiles and PDF drawings are read on your computer and the project is kept in your browser until you save it as a file.