The 14-point schedule quality check

The 14-point assessment, first set out by the US Defense Contract Management Agency (DCMA), is the most widely used test of whether a programme is well built: is every activity linked, are there leads and long lags, too many hard constraints, too much float, activities too long to manage? Planners, clients and claims consultants use it to review programmes before they are accepted. Metre2 Programme Studio Pro runs all 14 checks against the usual thresholds, shows the activities behind each and writes a Word report.

4 stepsProVideo 25 seconds

What you need

Step by step

1

Run the check

Open Analyse > 14-point. The result opens in the bottom panel: how many checks passed, failed and could not be assessed, at the programme's data date and against its baseline.

Run the check - Metre2 Programme Studio
2

Read the 14 checks

Each check has what it measures, the result and the target: logic (open ends), leads, lags, relationship types (finish-to-start), hard constraints, high float and high duration (over 44 days), negative float, invalid dates, resources, missed tasks, the critical path test, the critical path length index (CPLI) and the baseline execution index (BEI).

Read the 14 checks - Metre2 Programme Studio
3

Look at what failed

Click a check to select the activities behind it, so you can look at them in the table and Gantt chart. Here 5.7% of relationships have a positive lag, against a target of 5%. A fail is a question to answer, not always a fault: a lag for concrete curing is fine, a lag standing in for missing activities is not.

Look at what failed - Metre2 Programme Studio
4

Save the report to Word

Choose Save to Word for the full assessment to send to the client or keep with the programme submission.

Save the report to Word - Metre2 Programme Studio

Tips

Frequently asked questions

What are the DCMA 14 points?

Logic, leads, lags, relationship types, hard constraints, high float, negative float, high duration, invalid dates, resources, missed tasks, the critical path test, the critical path length index and the baseline execution index. They were developed by the US Defense Contract Management Agency to assess the quality of project schedules.

What are the usual thresholds?

For example: no more than 5% of open activities missing a predecessor or successor, no leads, no more than 5% of relationships with lags, at least 90% finish-to-start, no more than 5% hard constraints, high float and high duration over 44 working days for no more than 5%, and a CPLI and BEI of at least 0.95.

Does a programme have to pass all 14?

No. The checks are indicators: a failure is something to explain or fix. Many good construction programmes fail one or two for sound reasons, such as curing lags or a long lead-in item.